(A)
Installation of a 750-bbl/day capacity
Condensate Fractionation Plant at
Kailashtilla Field
A
feasibility study for setting up a
750-bbl/day condensate fractionation
plant aimed at fractionating Jalalabad
Gas Field’s condensate into motor
spirit, kerosene oil and diesel has
has already been completed. This is
a self financed project. DPP has been
prepared and presented to the company
board.
|
|
|
|
|
(B)
Drilling of five new wells at Kailashtilla,
Rashidpur and Sylhet (Haripur) Field
3-dimensional
seismic survey would be conducted
at Kailashtilla, Rashidpur and Sylhet
(Haripur) Fields. The project is aimed
at delineating the extent of gas reserve
at RGF, KGF and HGF. The project would
be completed in December 2010. Based
on the results of 3-D Seismic Survey,
2 new wells at KGF, 2 new wells at
RGF and 1 new well at HGF would be
drilled in future with a view to enhancing
the gas production from these fields.
|
|